Nigeria re-awards $5.8 billion Mambilla hydroelectric power plant contract to Chinese state firm
August 30, 20172K views0 comments
Nigeria has approved the construction of a $5.8 billion hydroelectric power plant by a Chinese state firm, the power minister said Wednesday, the latest in a series of Chinese deals since the project was first envisioned decades ago.
The project, if completed, could provide a much-needed source of energy for Nigeria. Despite its wealth of crude oil, Africa’s largest economy has long struggled with rickety power infrastructure, leaving many homes and businesses dependent on costly and inefficient fuel-powered generators.
The 3,050 megawatt (MW) Mambilla hydroelectric plant has been planned for over three decades. Various administrations have pledged to begin work, signing contracts and memoranda of understanding but next to nothing has been done.
Nigeria’s cabinet signed off on the award of the contract to build Mambilla to the China Civil Engineering Construction Corporation (CCECC), Babatunde Fashola, the minister of power, works and housing, told reporters in Abuja.
Read Also:
- Botched and bungled exercise that’s Nigeria’s 2025 budget
- Nigeria at 64, where individual comfort trumps national greatness (2)
- Inflation storm rages on in Nigeria as October rate hits 33.88%
- Nnaji, to establish Robotics, Artificial Intelligence Institute in Nigeria
- Nigeria’s inflation, cost of living crisis vs. minimum wage
China’s Export-Import Bank will provide 85 percent of the funding and Nigeria’s government will supply the remaining 15 percent for the joint venture, Fashola said, adding that construction should take around six years.
“The scope of works is very extensive, it requires the construction of four dams,” he said.
“It will involve a lot of preparatory work (and) resettlement … It will also help Nigeria strike a very big blow on the climate change issue.”
See also: Satellite data hint Nigeria’s economy is improving
But environmental groups raised concerns about the project.
“Many fear that Mambilla will go the way of previous large development projects (including large hydropower projects) where contracts are meted out but projects are never built,” International Rivers campaign group wrote on its official site.
“If the Mambilla dam project does continue, it could mean disastrous environmental and social impacts for those already living in poverty along the banks of the Benue River,” it said.
The Mambilla Dam is said to be the biggest on the continent of Africa expected to generate 12, 000 Mega Watts of electricity if fully operational. The Mambilla project was bided for and won by Tafag Nigeria Limited in 2006 with a total score of 82 percent coming first among equals, but the contract was awarded to a Chinese firm, which was later cancelled.